Perbaikan Turap Longsor Kali Sunter Capai 30 Persen
.
photo Nurito - Beritajakarta.id

Sunter River Retaining Wall Repair Targeted to Finish in Mid-March

Repair work on collapsed Sunter River's retaining wall, RT 10/04 Pondok Bambu, Duren Sawit, East Jakarta that has been carried out since February is targeted to finish in mid-March.

We are targeting it to finish it in the next two weeks

Duren Saat Sub-district SDA Task Force Head, Achmad Dody Firmansyah mentioned, collapsed retaining wall that had to be repaired was about 14.5 meters long and 2.5 meters high. It collapsed due to flood on Tuesday (2/16). Currently the repair work progress has reached 30 percent.

"We repair it by installing stone gabions. We are targeting it to finish it in the next two weeks," he stated, Monday (3/1).

Residential Sheet Pile in Duri Selatan Repaired

His side deployed 9 SDA Task Force personnel to repair it which were sometimes also assisted by 5 PPSU personnel.

"Repair work sometimes hampered by rising water level of Sunter River during heavy rain," he said.

Linked News
Popular News indeks
  1. Transjakarta Officially Opens School for Bus Drivers

    access_time20-11-2024 remove_red_eye1065 personAldi Geri Lumban Tobing
  2. Parekraf Agency Introduces Jakarta as a Global City at IBTM World 2024

    access_time23-11-2024 remove_red_eye938 personAldi Geri Lumban Tobing
  3. Acting Governor Teguh: Coastal Seawall Construction Begins in 2025

    access_time20-11-2024 remove_red_eye928 personFolmer
  4. Jakarta Baznas Bazis Ready to Support Disaster Preparedness

    access_time25-11-2024 remove_red_eye765 personAldi Geri Lumban Tobing
  5. Gubernatorial Election Logistics in Seribu Island Distributed

    access_time26-11-2024 remove_red_eye590 personBudhi Firmansyah Surapati